Summary: Display both % of work completed over planned and % of work completed over total recipes to be updated
Product: [Yocto Project Subprojects] Recipe Reporting System (RRS) Reporter: Belen Barros Pena <belen.barros.pena>
Component: Recipe Reporting System (RRS)Assignee: Mariano Lopez <mariano.lopez>
Status: VERIFIED FIXED QA Contact: Bogdan Alexandru Voiculescu <bogdanx.a.voiculescu>
Severity: enhancement    
Priority: Medium CC: benjamin.esquivel, bogdanx.a.voiculescu, sgw
Version: unspecified   
Target Milestone: 1.9 M3   
Hardware: x86   
OS: Multiple   
Whiteboard: GUI design available
OS type for building Yocto: --- Type of Regression: ---
Verified: Documentation change: No (bug/feature does not impact docs)
Attachments:
Description Flags
Design - Display % of work completed and planned none

Description Belen Barros Pena 2015-07-16 10:41:18 UTC
It turns out there are 2 meaningful percentages to show per milestone (and release):

1. Percentage of planned work completed (100 recipes not updated at the beginning of the milestone, with 80 updated during the milestone, means 80% of the planned work completed)

2. Percentage of total work completed (106 recipes not updated at the current point in the milestone, with 80 updated during the milestone, means 75% of total work completed)

This happens because new recipes can become out of date during the milestone itself (they can be considered "unplanned work").

The RRS should display both percentages, and explain their meaning.
Comment 1 Benjamin Esquivel 2015-08-12 19:46:57 UTC
Waiting for design
Comment 2 Belen Barros Pena 2015-08-13 14:14:39 UTC
Created attachment 2664 [details]
Design - Display % of work completed and planned
Comment 3 Belen Barros Pena 2015-08-13 14:14:56 UTC
Design done
Comment 4 Benjamin Esquivel 2015-08-13 16:13:36 UTC
Thank you Belén!

All yours Mariano :)
Comment 6 Bogdan Alexandru Voiculescu 2015-09-03 12:28:32 UTC
verified
Comment 7 Bogdan Alexandru Voiculescu 2015-09-03 12:28:50 UTC
verified